Mojave Solar Project

From Infogalactic: the planetary knowledge core
Jump to: navigation, search

<templatestyles src="Module:Hatnote/styles.css"></templatestyles>

Mojave Solar Project
Mojave Solar Project is located in California
Mojave Solar Project
Location of Mojave Solar Project in California
Country United States
Location Mojave Desert, California
Coordinates Lua error in package.lua at line 80: module 'strict' not found.
Status Operational
Construction began September 2011
Commission date December 1, 2014
Solar field
Type CSP
CSP technology Parabolic trough
Collectors 2256 (SCAs)
Total collector area 1,559,347 square metres (385.323 acres)
Site area 1,765 acres (7 km2)
Site resource 2,685 kW·h/m2/yr
Power generation
Nameplate capacity 280 MW
Capacity factor 28%
Annual generation 617 GWh

The Mojave Solar Project (MSP) is a concentrated solar power (CSP) facility in the Mojave Desert in California, about 20 miles (32 km) northwest of Barstow. Surrounding the hamlet of Lockhart, Mojave Solar is adjacent to Harper Lake and the SEGS VIII–IX solar plant. The site was originally reserved for the planned, never built, SEGS IX and XII. For 15 years following its construction in 1990, this was the largest commercial solar power plant in the world, generating around 160 megawatts at its peak. It is one of three separately owned sites within 40 miles of one another, that make up the nine solar fields in the Solar Electric Generating System (SEGS #1 and 2 are at Daggett, and #3 through 7 are at Kramer Junction). Harper Lake was the last of these built, and is designated as SEGS #8 and 9. It is still online, but has been surpassed by other newer facilities, including the Mojave Solar Project.[1] MSP, with a combined nameplate capacity of 280 MW (net 250 MW), is made of two, independently-operable, solar fields. The power plant cost an estimated $1.6 billion in total and entered commercial operation in December 2014.[2] The developer, Abengoa, has successfully secured a $1.2 billion loan guarantee from the US government for the project.[3][4][5] The plant is expected to generate 617,000 MWh of power annually, enough power for more than 88,000 households and to prevent the emission of over 430 kilotons of CO2 a year.[6] Pacific Gas & Electric has agreed to a 25-year power purchase agreement.[7]

The plant was commissioned on 1st December, 2014.[8]

Technology

The array of parabolic troughs at the Mojave Solar Project site in their stow position.

Using the desert's solar thermal energy, the facility generates steam in solar steam generators, which expands through a steam turbine generator to produce electrical power from twin, independently operable solar fields, each feeding a 125 MW power island. Generation is provided 100% from sun, no supplement from fossil-based energy sources. There is a gas-fired auxiliary boiler, for each field, only to provide equipment and heat-transfer fluid (HTF) freeze protection, when temperatures fall below 54 °F (12 °C).

The details of the parabolic trough used in the project.

The power cycle is a Rankine-with-reheat thermodynamic cycle from heat supplied via heat-transfer fluid, solar field heated up to 740 °F (393 °C). When operating, the transfer fluid enters the solar field at about 520 °F (271 °C). The steam generator steam exit temperature is about 720 °F (382 °C).

Each field utilizes 1128 solar collector arrays (SCA) sited on about 710 acres (290 ha). Each SCA, model E2 from Abengoa (derived from Luz's LS-3), is 125 metres (410 ft) long and is made of 10 solar collector elements (SCE), 12 metres (39 ft) long each and 5.76 metres (18.9 ft) aperture. The E2 steel frame collector with monolithic glass reflector panels, yields a total aperture area of 691.2 square metres (7,440 sq ft). That makes a total of 779,674 square metres (8,392,340 sq ft) aperture each solar field, 1,559,347 square metres (16,784,670 sq ft) total for the plant, operating about 3,024 hours per year.

Cooling is provided by wet cooling towers; water for the towers and solar collector washing, is supplied from onsite groundwater wells. Water from condensed steam exits the cooling tower pump at about 80 °F (27 °C), before cycling back to the steam generator.

Production

Mojave Solar Project production is as follows (values in MW·h).[9]

Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
2015 4,816 28,254 49,104 57,830 49,132 43,618 64,353 63,367 57,559 37,406 32,818 15,319 503,576
2016 4,635 4,635
All-Time Total 508,211

See also

References

  1. http://clui.org/project-page/13338/13344
  2. csp-world.com Abengoa's Mojave 250 MW CSP plant enters commercial operation, 2 December 2014
  3. Lua error in package.lua at line 80: module 'strict' not found.
  4. Lua error in package.lua at line 80: module 'strict' not found.
  5. Abengoa Solar Abengoa Solar - The Mojave Solar Project
  6. Lua error in package.lua at line 80: module 'strict' not found.
  7. Lua error in package.lua at line 80: module 'strict' not found.
  8. Lua error in package.lua at line 80: module 'strict' not found.
  9. Lua error in package.lua at line 80: module 'strict' not found.

External links

  • Lua error in package.lua at line 80: module 'strict' not found.
  • Lua error in package.lua at line 80: module 'strict' not found.
  • Lua error in package.lua at line 80: module 'strict' not found.
  • Lua error in package.lua at line 80: module 'strict' not found.